1: <?xml version="1.0" encoding="utf-8"?>
2: <MSProject>
3: <Mappings>
4: <Mapping WorkItemTrackingFieldReferenceName="System.AreaPath" ProjectField="pjTaskOutlineCode9" />
5: <Mapping WorkItemTrackingFieldReferenceName="System.AssignedTo" ProjectField="pjTaskResourceNames" />
6: <Mapping WorkItemTrackingFieldReferenceName="System.Id" ProjectField="pjTaskText10" ProjectName="Work Item ID" />
7: <Mapping WorkItemTrackingFieldReferenceName="System.IterationPath" ProjectField="pjTaskOutlineCode10" />
8: <Mapping WorkItemTrackingFieldReferenceName="System.Reason" ProjectField="pjTaskText14" />
9: <Mapping WorkItemTrackingFieldReferenceName="System.Rev" ProjectField="pjTaskText23" />
10: <Mapping WorkItemTrackingFieldReferenceName="System.State" ProjectField="pjTaskText13" ProjectName="State" />
11: <Mapping WorkItemTrackingFieldReferenceName="System.Title" ProjectField="pjTaskName" />
12: <Mapping WorkItemTrackingFieldReferenceName="System.WorkItemType" ProjectField="pjTaskText24" />
13: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Common.Priority" ProjectField="pjTaskText19" ProjectName="Work Item Priority" />
14: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Common.StackRank" ProjectField="pjTaskNumber1" />
15: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Scheduling.CompletedWork" ProjectField="pjTaskActualWork" ProjectUnits="pjHour" IfSummaryRefreshOnly="true" />
16: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Scheduling.FinishDate" ProjectField="pjTaskFinish" PublishOnly="true" />
17: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Scheduling.OriginalEstimate" ProjectField="pjTaskBaselineWork" ProjectUnits="pjHour" IfSummaryRefreshOnly="true" />
18: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Scheduling.RemainingWork" ProjectField="pjTaskRemainingWork" ProjectUnits="pjHour" IfSummaryRefreshOnly="true" />
19: <Mapping WorkItemTrackingFieldReferenceName="Microsoft.VSTS.Scheduling.StartDate" ProjectField="pjTaskStart" PublishOnly="true" />
20: <Mapping WorkItemTrackingFieldReferenceName="ElBruno.WbsCode" ProjectField="pjTaskWBS" PublishOnly="true" />
21: <LinksField ProjectField="pjTaskText26" />
22: <SyncField ProjectField="pjTaskText25" />
23: </Mappings>
24: </MSProject>